The State of Illinois on Monday released two energy reliability reports aimed at planning for the region's electric resource adequacy and maintaining reliable, affordable service while reducing emissions.

The Illinois Commerce Commission released its Integrated Resource Plan report, required under the Clean and Reliable Grid Affordability Act. The ICC said the report models potential energy futures and recommends approaches for achieving resource adequacy. A docketed approval proceeding is expected to open Thursday, Nov. 19, 2026, and could run six to 12 months.

At the same time, the Illinois Power Agency and the Illinois Environmental Protection Agency issued a draft Resource Adequacy Mitigation Plan under the Climate and Equitable Jobs Act. The draft recommends extending applicable CEJA emissions-reduction deadlines for eligible gas- and oil-fired units through the end of the 2032-2033 planning year. Coal-fired units, which the state said produce much more pollution, are not included in the proposed extensions.

"Energy affordability and sustained resource adequacy are top priorities at the ICC," said ICC Executive Director Jonathan Feipel. "The state's new integrated resource planning process allows us to keep a pulse on Illinois' evolving energy needs, and the IRP report published today will provide valuable insights on how to keep Illinois moving toward a clean and affordable energy future."

"The draft plan places resilience, stability, and energy affordability front and center while continuing to drive forward the state's clean energy goals," said IPA Director Brian Granahan.

The state said the reports differ in scope. The mitigation plan focuses on near-term emissions restrictions, while the IRP lets the ICC consider broader resource adequacy recommendations over a 20-year outlook. The state said Illinois is the first restructured state in the region to use an IRP to address resource adequacy concerns, having historically relied on competitive power markets. Officials cautioned that potential capacity shortfalls identified in the analysis should not be read as a prediction of future outages.

Integrated Resource Plan report

The ICC said the IRP report is meant to give regulators, policymakers, utilities and other stakeholders a common understanding of Illinois' long-term energy outlook. It examines how different resource mixes, transmission expansion, plant retirements and emerging technologies could affect affordability, reliability, clean energy standards and equity.

Key takeaways from the report include:

  • Illinois' electric system does not operate in isolation and works with two regional grid operators spanning multiple states, with resource adequacy challenges driven primarily by data center load growth.
  • Illinois can achieve a reliable clean power system using a diverse pool of resources, balancing affordability, reliability and emissions reductions.

The report also weighs factors including renewable portfolio standard goals, demand-side and data center load flexibility, battery storage, fossil fuel plant retirement schedules, retention of the current nuclear fleet, new reactors and interregional transmission development.

ICC staff and participating agencies are expected to submit direct testimony on specific IRP recommendations, with a final decision expected by November 2027.

Draft Resource Adequacy Mitigation Plan

The IPA, IEPA and ICC were tasked under CEJA with preparing a Resource Adequacy Study, published in December 2025, which identified a risk of resource adequacy shortfalls for Illinois and the region over the coming decade. The draft mitigation plan responds to those constraints and assesses whether to allow certain plants to keep operating, including with reduced emissions or as emergency backup.

Key findings include:

  • Resource adequacy needs continue across the PJM and MISO regions of Illinois.
  • Retaining certain CEJA-covered units could support reliability by running only during a limited number of high-risk hours.
  • Most reliability and affordability benefits from extending closure deadlines come from gas and oil units, not coal.
  • Near-term retirements could lead to new natural gas generation outside Illinois and could increase consumers' exposure to capacity market costs.

The draft proposes extending applicable CEJA deadlines for certain covered units through at least the end of the 2032-2033 planning year, limited to what is necessary to address identified needs. Authorization of any extension lies with the ICC through an order following litigation of the plan.

How to comment

The mitigation plan is a draft released for stakeholder feedback and is not final. The IPA and IEPA are accepting comments from Nov. 16, 2026, through Jan. 15, 2027, at 5 p.m. Central time. Comments must be submitted to the IPA at IPA.ContactUs@illinois.gov. The agencies will have 30 days to review comments before filing an updated plan with the ICC for approval.

Questions about the IRP report should be directed to the ICC, and questions about the mitigation plan to the IPA. Consumers who need help resolving a utility dispute can call the ICC at 800-524-0795.